Impact Window Installation Timeline: What to Expect in Broward County

Short answer: most residential impact window installations take 1 to 3 days. A standard three-bedroom home usually takes 1–2 days, and a larger home with 20 or more openings may take 3–5 days. The full timeline — from your first consultation to the final inspection — depends on how long the permit review and the manufacturing lead time take, and both vary. You get a confirmed timeline for your home at the consultation stage, before work begins.

By Dave Meadors

The timeline at a glance

StepWhat happensTiming
1. Consultation and measureFree in-home estimate; every opening measuredOne visit; confirmed timeline given at this stage
2. Proposal and contractItemized written quote; build plan approved and contract signedAfter the consultation
3. Permit package and Broward County permitPermit package prepared in-house; application filed with the city; review and approvalVaries by city and workload — no fixed number
4. Ordering and manufacturingProducts ordered to your exact measurementsVaries by product line, size, and custom shapes
5. Installation day(s)In-house crew installs your windows and doorsMost homes 1–3 days; standard 3-bedroom 1–2 days; 20+ openings 3–5 days
6. Final inspectionInspector verifies the installation against the approved permitScheduled and coordinated by Broward Impact
7. Final walkthroughYou walk every opening with the crew; permit closeoutAfter the final inspection

Step 1: Consultation and measure

It starts with a free in-home estimate. Broward Impact measures every opening, brings product samples, and gives you an itemized written quote — so you know what each window and door costs before you commit to anything. There is no obligation.

This visit is also when you get your timeline. Broward Impact gives you a confirmed timeline at the consultation stage, before work begins — based on your home, the products you choose, and the permit process in your city. That confirmed timeline is the one to plan around, not any general number on this page.

Step 2: Proposal and contract

After the consultation, the proposal is drawn up from the measurements: the products for each opening, the itemized pricing, and the build plan. Broward Impact’s process calls this step the Proposal/Contract Sign Off — the build plan is approved and the contract is signed, and only then does the project move to the permit package and the product order. For payment timing and options, see the financing page.

If you are using the My Safe Florida Home program, this is also the stage where the grant paperwork and the approved scope are matched to the quote — Broward Impact works with My Safe Florida Home grant recipients and explains the program as it applies to your home. See Broward Impact’s My Safe Florida Home page for how that program works. If you are paying through PACE financing, that approval is settled at this stage too, before the permit package and the product order.

Step 3: Permit package and the Broward County permit

Every impact window and door installation in Broward County needs a permit. Broward Impact develops the permit package in-house: elevations and floor plans that call out each opening, the product approvals (the Miami-Dade Notice of Acceptance, or NOA, for each product), and the installation details. The company then manages the permit process for you — filing the application, scheduling, and coordinating the inspection — at no additional charge.

The permit steps, as Broward Impact describes them, are: consultation and measurement, product selection, permit application, permit review, permit approval, installation scheduling, final inspection, and closeout. During review, the city checks the NOA and product approvals, the opening sizes, and the anchoring details. Permit fees vary by city.

How long does the permit take? There is no fixed number published, and no one can give you one honestly: the review timeline varies by city and by workload. That is the part of the timeline most likely to stretch, and it is also the part you do not have to manage yourself. For the full permit process, see Broward Impact’s impact window permits guide for Broward County.

Step 4: Ordering and manufacturing

Once the contract is signed, the material is ordered to meet the specific requirements of your project — each window and door is made to the measurements taken at your home. Manufacturing lead time is the other variable in the timeline: it varies by product line, by size, and by whether any opening needs a custom shape. Arched, round, or otherwise custom-shaped windows require custom fabrication, which takes longer than a standard size.

No day count is promised here, because none is published. The lead time for your products is part of the confirmed timeline you are given at the consultation stage, and it is the reason the total time from signing to installation day is described as “it depends” rather than as a fixed number of weeks.

Step 5: Installation day(s)

Installation is performed in-house by our in-house installation team — Broward Impact uses no subcontractors for installation. The crew works through your openings in the order agreed when the installation was scheduled, and you will be told what will be finished each day.

Most residential installations take 1 to 3 days. A standard three-bedroom home usually takes 1–2 days, and a larger home with 20 or more openings may take 3–5 days. The old windows and doors are removed, the new impact units are set and sealed, and installation pricing includes basic cleanup.

How to prepare for installation day: clear access to every opening, move furniture and fragile items away from the windows and doors, and plan for noise and dust while the work is under way. Keep children and pets away from the work areas. At the start of the first installation day, ask the crew how they will protect your floors and furnishings around each opening and what cleanup is included — so you know what to expect before the first window comes out.

Step 6: Final inspection

After installation, the work is inspected. Broward Impact coordinates the scheduling of the final inspection. The inspector verifies that the installation matches the approved permit — the product approvals, the opening sizes, and the anchoring — and that the work was done to the approved plan.

If the inspector flags something, it is corrected and the inspection is repeated. That is a normal part of the process, not a sign that something went wrong with your home: the inspection exists to catch exactly those items, and the permit is not closed out until the installation passes.

Step 7: Final walkthrough and closeout

The last step is the final walkthrough: you walk every opening with the crew, check that each window and door opens, closes, and locks as it should, and ask any questions while the crew is still there. After the final inspection passes, the permit is closed out — the closeout step Broward Impact lists at the end of its permit process.

Keep your paperwork together: the itemized quote, the permit, and the product approvals for your windows and doors. Those documents are what a future buyer, insurer, or inspector will ask for, and they are the record that your installation was permitted and inspected.

What can change the timeline?

  • Permit review time. Review timelines vary by city and by workload, and permit fees vary by city.
  • Product lead time. It varies by product line, by size, and by custom shapes — arched, round, or custom-shaped windows require custom fabrication.
  • Structural work. If an opening needs structural modifications, that work is quoted case by case, and it can add time as well as cost.
  • Access and size. Second-floor openings and hard-to-reach openings take longer to install, and a larger home simply has more openings to work through — a home with 20 or more openings may take 3–5 days to install.
  • Inspection scheduling. The final inspection has to be scheduled with the city, and Broward Impact coordinates that scheduling for you.

None of these is a reason to guess at a date. The confirmed timeline you are given at the consultation stage takes your home, your products, and your city’s permit process into account.

Frequently asked questions

How long does impact window installation take in Broward County?

Most residential installations take 1 to 3 days. A standard three-bedroom home usually takes 1–2 days, and a larger home with 20 or more openings may take 3–5 days. The full timeline, from consultation to final inspection, also depends on the permit review and the manufacturing lead time, which both vary — you get a confirmed timeline for your home at the consultation stage, before work begins.

How long does the permit take for impact windows in Broward County?

There is no fixed number published, and no one can give you one honestly: the permit review timeline varies by city and by workload, and permit fees vary by city. Broward Impact develops the permit package in-house and manages the filing, scheduling, and inspection coordination for you, at no additional charge.

Who handles the permit and the inspections?

Broward Impact does. The company develops the permit package in-house — elevations and floor plans calling out each opening, with the product approvals for each product — and manages the permit process, including filing the application, scheduling, and coordinating the inspection. Installations are performed in-house by our in-house installation team, with no subcontractors.

What happens at the final inspection?

The inspector verifies that the installation matches the approved permit — the product approvals, the opening sizes, and the anchoring — and that the work was done to the approved plan. If the inspector flags something, it is corrected and the inspection is repeated, and the permit is not closed out until the installation passes.

What if an opening needs structural work?

Structural modifications are quoted case by case, and they can add time as well as cost. They are assessed during the consultation and measurement stage, so they are in the itemized written quote and the confirmed timeline before work begins — not discovered as a surprise on installation day.

When do I get a confirmed timeline for my home?

At the consultation stage, before work begins. Broward Impact measures your openings, quotes the project in writing, and gives you a confirmed timeline based on your home, the products you choose, and the permit process in your city.

Get your free in-home estimate